Loading...
Railway scales in mixed metal-concrete structure with above-ground mounting, directly on the railway infrastructure (without concrete pouring works in situ) relocable, PREMIUM HEAVY-DUTY. Static weighing.
The structure of the C-DECK weighing platform is mixed metal-concrete with metal beams - the active weighing component - mounted on a prefabricated concrete foundation type C45 / 55 according to DIN 1045 which is installed directly on the broken stone infrastructure of the railway.
2 or 3 modules
8 or 12 loadcells
Lengths: 5+[5]+5m, respectively 5+5+[5]+5m
| LENGTH | 15m | 20m |
|---|---|---|
| PLATFORM | METAL-CONCRETE | |
| CAPACITY (60t/module) [t] | 120 | 120 |
| CLC [k] | 80 | 80 |
| ARROW F [mm] | 1:950 | 1:950 |
| CONSUMPTION | 15m | 20m |
|---|---|---|
| METAL [t] | 10,4 | 15,6 |
| PREFABRICATED CONCRETE [mc] | 8,0 | 13,5 |
The railway scale can have any length in the range 12..60m, length achieved by combining the active weighing modules of 5, 6 or 7m and positioning them at a variable distance in the range 0 / 3..6m (idle area indicated in square brackets) .
Sizing is done by optimizing the placement of the active weighing modules alternating with the inactive (free) areas between them in order to obtain a configuration that allows weighing a train with a minimum (optimal, zero) of untied wagons (optimally, without untying any wagon).
The calculation requires that the bogie axis be positioned as close as possible to the center of the module. According to Instruction 314 of the rules and tolerances for the construction and maintenance of the railway (page 84), no rail coupons below 3m in length are allowed. Therefore, 3m is the minimum length of a C.F. For the sizing process, it is absolutely necessary a list (as complete as possible) with the type of wagons that will transit the railway scale.


| GABARITIC TRANSPORT | CRANE [t] | WEIGHT MODULE [t] |
|---|---|---|
| 2 trucks | 25t | 3,44t |